carpet
Design and drafting can start before take over of the premises, as soon as confirmation of renting / purchasing the premises
Confirmation of master floor plan is essential, after which all other design work, or renovation work can begin
Major change of design or completed work items will seriously affect the completion date, and should be avoided
Project completion can be speeded up by night work, but cost will be raised significantly
Carpentry work and delivery of tailor made furniture / cabinet are determining procedures, which affect other works and project completion
Project completion will be significantly affected if management company apply strict limitation policy on noisy work procedures
Homepage Who We Are What We Do Why Us What We Have Done What You Should Do How Much You Will Spend When To Start And Finish Whom We Have Served What You Will Ask How To Contact Us
  DESIGN & DRAFTING PREPARATION TO START RENOVATION MAKING UP DEFECTS

300 - 600 SF

7 - 20 DAYS 2 - 5 DAYS 30 - 50 DAYS 1 - 4 DAYS
600 - 1,000 SF 14 - 20 DAYS 3 - 6 DAYS 40 - 60 DAYS 2 - 5 DAYS
1,000 -1,800 SF 21 - 30 DAYS 3 - 7 DAYS 45 - 80 DAYS 4 - 10 DAYS

> 1,800 SF

21 - 45 DAYS 4 - 8 DAYS 50 - 85 DAYS 6 - 15 DAYS